Monday, March 28, 2011

Conduit for new electrical service was bored under the parking lot this morning. Tarps were added to the roof on Saturday to keep the rain out. The old folding partition trusses have been taken out and replaced.


Friday, March 25, 2011

Roof sheathing has begun.

Simpson straps have been place per the plans before the sheathing covers them.



Thursday, March 24, 2011

Framing continues on the addition


Plumbers have started digging a trench to install the sewer line to tie into the existing.


Wednesday, March 23, 2011

Trusses were set by crane yesterday morning
Framing on the building continues

Tuesday, March 8, 2011

Slab for the chuch was poured this morning.









Sidewalks along North Geronimo were poured this morning. A space was left out where a trench drain will be added later.









Monday, March 7, 2011

Column footings have been excavated and rebar has been placed. We will pour tomorrow. Sidewalks along North Geronimo have been formed, we will add W.W.F. and pour them.

Slab is ready to pour and has been inspected by the county, architect, and Nova engineering.


Dowels were added to the existing concrete to tie the slabs together.




Friday, March 4, 2011

Vapor barrier is installed, #3 rebar is being placed for slab reinforcement.

Thursday, March 3, 2011

All the stone has been placed and graded down to subgrade. Termite treatment is going down.

East side of the property has been graded for preperation of sidewalk.
Last of the interior footings were poured today.

4" of stone is being installed in preperation of the slab.