Tuesday, September 27, 2011

9-27

Cabinets and countertops have been installed in the library
Storage cabinets have been installed in the Relief Society and Primary rooms.
Trim has beed installed in the gym as well as the doors have been hung.
Storefronts have Finally arrived and are being installed.

Wednesday, September 14, 2011

09-14

Pews have arrived and installed. Cornell foldin partition has been installed.
Counter tops and sinks have been installed in the bathrooms as well as the grab bars and the mirrors
Landscaping on the west end of the building has been completed

Friday, September 9, 2011

update

Rostrum has been installed as well as the carpet in the chapel and rostrum
Carpet in the hallways, chair-rail should be installed next week
The gym floor has been sanded and one coat of sealer has been applied
Plumbing fixtures are being installed

Compost is down and planting is about to begin.

Tuesday, September 6, 2011

update

Mow Strips have been installed, irrigation lines are being installed
Ramp has been poured to transition 2" up to the wood floor in the multi-purpose room
2 new pendent lights have been hung in the chapel to match existing. ceiling has been textured, vinyl has been removed and the chapel has been painted
Sacrament table and other rostrum mill work is being installed
Basketball goal has been hung, sisal has been installed, safety padding on the wall has been hung and the hardwood floor continues to be nailed down.

Thursday, July 21, 2011

Progress

Drywall on the walls of the halls and all of the class rooms has been hung and is being finished.

Drywall on the chapel ceiling is installed.

Duct continues to be installed over the class rooms

Ceiling grid is installed in the class rooms except for the primary and relief society rooms.
Mechanical pads have been removed and lowered to be below the finish floor level.

Thursday, July 7, 2011

Update

Brick has been installed on the building as well as the roof
Curbs have been poured new sidewalk has been poured and asphalt has been installed in the new parking area
South side of the building
Drywall is being installed. sprinkler system is underway as well as the duct work in the mezzanine. Door frames have been installed and insulated.
Elec work in the cultural hall continues, speakers, can lights, and surface mounted lights are being roughed in. Basketball support hangers are in place. Sprinkler heads are in.

Friday, May 6, 2011

Update

Sod has been installed by the grader along the east and west side of the sidewalk that runs next to N Geronimo st. to prevent any erosion.The grader has taken several excess loads of dirt away and has rough graded the back of the church.
Fascia and soffit are being installed on the addition
The new soffit.