Thursday, July 21, 2011

Progress

Drywall on the walls of the halls and all of the class rooms has been hung and is being finished.

Drywall on the chapel ceiling is installed.

Duct continues to be installed over the class rooms

Ceiling grid is installed in the class rooms except for the primary and relief society rooms.
Mechanical pads have been removed and lowered to be below the finish floor level.

Thursday, July 7, 2011

Update

Brick has been installed on the building as well as the roof
Curbs have been poured new sidewalk has been poured and asphalt has been installed in the new parking area
South side of the building
Drywall is being installed. sprinkler system is underway as well as the duct work in the mezzanine. Door frames have been installed and insulated.
Elec work in the cultural hall continues, speakers, can lights, and surface mounted lights are being roughed in. Basketball support hangers are in place. Sprinkler heads are in.