The sidewalks at the back of the building have been removed in order to expand the parkinglot and the building.

The building pad has been stripped down to suitable soils. 4 density tests were taken yesterday, the results were, 98% 98% 99% and 100%. We are ready for fill material.

The sidewalk at the front of the building was removed and a silt fence was installed for erosion control.